An HT connection is not a longer version of an LT one. It is a different file, with a different set of drawings, a technical feasibility study at the DISCOM, an agreement to execute, a substation to build at your end, and a statutory safety approval before anyone is allowed to energise it. Most of the elapsed time is spent waiting in offices, not working on site.
Gujarat raised the low-tension ceiling from 100 kW to 150 kW in the 2024 amendment to the Electricity Supply Code, so some loads that would once have been forced onto HT can now stay LT. Above that ceiling, HT is not a choice.
We run the whole thing: work out the load and the route, prepare and submit the application with the drawings the DISCOM actually asks for, follow the feasibility and the estimate, execute the agreement, build the line and the substation, and take the installation through the Electrical Inspector so it can be charged.