This is the safety gate. Under the Central Electricity Authority safety regulations, an installation operating above the voltage notified by the State Government has to be approved by the Electrical Inspector before supply is commenced — and again after a long shutdown or a material extension. It is not a formality the DISCOM can waive, and no amount of finished site work substitutes for it.
What the Inspector is checking is whether the installation as built matches the drawings, and whether it is safe to energise: clearances, earthing resistance actually measured, protection sized and set, interlocks, danger boards, rubber mats, and the test results to back all of it. The approval is granted against evidence, not against assurance.
The economics of this stage are simple. Every lap of the observation loop is weeks. Designing to what the Inspector will look for, and having the test reports ready before the visit rather than after, is the difference between one inspection and three.